The application for GPCB consents is made online. Below mentioned is the full registration procedure:
Step 1: Industry Classification
The applicant must first check the category of the unit — Red, Orange, Green, or White — to know which type of consent applies.
Step 2: Make a GPCB sign-in
Only the industry owner needs to register on the official GPCB website and set up login details.
Step 3: Prepare Required Documents
It’s important for the applicant to collect all necessary documents. This includes land proof, layout, manufacturing components and pollution control plans.
Step 4: File Application for CTE
For new units, CTE is applied first. Details such as water source, fuel type, emissions, and treatment systems must be submitted.
Step 5: Scrutiny and Inspection
GPCB may ask for changes or conduct a site visit to verify the unit’s plan. Corrections must be made as per the board’s suggestions.
Step 6: Approval of CTE
If everything is fine the board issues the Consent to Establish. This remains valid for a set time period based on category.
Step 7: Apply for CTO
After setup, the applicant must submit the CTO form along with proof of installed control systems and trial runs.
Step 8: Grant of Consent to Operate
On successful review, GPCB issues the CTO with specific guidelines and reporting requirements.